Pitkin County, CO

62 public highway bridges

Pitkin County Bridge Snapshot

Pitkin County, Colorado contains 62 public highway bridges in the FHWA National Bridge Inventory. Roughly 38.7% are rated “Good,” 58.1% “Fair,” 3.2% “Poor,” and 3.2% are classified as structurally deficient — the federal designation for spans whose deck, superstructure, or substructure has been rated 4 or below on the 0–9 NBI scale. Structurally deficient does not mean unsafe to cross; it means the bridge is on the priority list for repair or replacement.

Inspections in CO are conducted by certified engineers from the state Department of Transportation on a 24-month cycle, and results are reported back to the FHWA each spring. The list below shows every NBI-tracked bridge in the county, sorted by inventory load rating. Use the “Sort by” controls to surface the lowest-rated spans first, and click any row for full inspection history, traffic counts, and condition trends.

Source: FHWA National Bridge Inventory. See methodology for full definitions.

62
Total Bridges
38.7%
Good
3.2%
Poor
3.2%
Structurally Deficient

Condition Distribution

Good
38.7% (24)
Fair
58.1% (36)
Poor
3.2% (2)
SD
3.2% (2)

All Bridges (62)

FDR 105-4A

Fair

Over: FRYINGPAN RV

NAST, Pitkin, CO

Built 1984 Load: 16.8 t ADT: 10

CTY RD 23/FDR 106

Fair

Over: ROARING FK RV

8 MI SE OF ASPEN, Pitkin, CO

Built 1957 Load: 19.8 t ADT: 40

FDR 310

Fair

Over: CRYSTAL RV

5.0MI N OF REDSTONE, Pitkin, CO

Built 1985 Load: 19.8 t ADT: 155

COUNTY ROAD 3

Fair

Over: CRYSTAL RIVER

E SH133 REDSTONE/MP51.4, Pitkin, CO

Built 1947 Load: 20.4 t ADT: 713

NEALE AVE

Fair

Over: ROARING FORK RIVER

2 BLK E OF HWY 82, Pitkin, CO

Built 1985 Load: 22.2 t ADT: 1,596

SH 82 ML

Fair

Over: CO RD, CASTLE CREEK

ASPEN, Pitkin, CO

Built 1961 Load: 22.3 t ADT: 25,000

FDR 504

Fair

Over: FRYINGPAN RV

NORRIE, Pitkin, CO

Built 1948 Load: 22.7 t ADT: 10

CR8/Watson Divide

Fair

Over: SNOWMASS CREEK

At Snowmass Circle Rd, Pitkin, CO

Built 1989 Load: 22.7 t ADT: 416

CR 4F/NAST COLONY

Fair

Over: FRYING PAN RIVER

.3 MI S OF CR 105/MP 31.8, Pitkin, CO

Built 1958 Load: 23.8 t ADT: 3

POWER PLANT RD

Fair

Over: CASTLE CREEK

JUST WEST OF MEADOWS RD, Pitkin, CO

Built 1973 Load: 24.3 t ADT: 12,818

MILL STREET

Fair

Over: ROARING FORK RIVER

4 BLK E OF HWY 82, Pitkin, CO

Built 1985 Load: 26.0 t ADT: 2,985

COUNTY ROAD 19

Fair

Over: ROARING FORK RIVER

1.1 MI N OF HWY 82, Pitkin, CO

Built 1992 Load: 27.3 t ADT: 3,783

CR 20/RED MTN RD

Fair

Over: HUNTER CREEK

jUST S PITKIN SIGN, Pitkin, CO

Built 1955 Load: 28.2 t ADT: 2,733

COUNTY ROAD 11

Fair

Over: SNOWMASS CREEK

S END OF COUNTY ROAD 11, Pitkin, CO

Built 1986 Load: 28.5 t ADT: 102

CO RD 4A/FS RD 400

Fair

Over: LIME CREEK

3 MI E OF RUEDI RESERVOIR, Pitkin, CO

Built 1955 Load: 29.9 t ADT: 41

SH 82 ML

Fair

Over: LOST MAN CREEK

INDPND PASS, 6 W OF SUMMI, Pitkin, CO

Built 1935 Load: 31.2 t ADT: 1,300

CR 13/MAROON CK RD

Fair

Over: MAROON CREEK

3.0 MI SW ASPEN/MP1.8, Pitkin, CO

Built 1988 Load: 31.4 t ADT: 751

FDR 121

Fair

Over: CASTLE CR

1.9MI S OF ASHCROFT, Pitkin, CO

Built 1972 Load: 32.7 t ADT: 10

FDR 105-6C

Fair

Over: FRYINGPAN RV

DAY USE AREA @ DAM, Pitkin, CO

Built 1985 Load: 32.7 t ADT: 50

COUNTY ROAD 15

Fair

Over: CRYSTAL RIVER

E OF SH 133 MO 53, Pitkin, CO

Built 1985 Load: 32.7 t ADT: 373

WOOD RD

Fair

Over: BRUSH CREEK

.01 MI S. OF BRUSH CR RD, Pitkin, CO

Built 2008 Load: 32.7 t ADT: 4,512

REDSTONE RANCH RD

Fair

Over: CRYSTAL RIVER

JUST E OF SH133 AT MP50, Pitkin, CO

Built 1992 Load: 34.4 t ADT: 161

CR 16/LOWER RVR RD

Fair

Over: ROARING FORK RIVER

JUST N OF STATE HWY 82, Pitkin, CO

Built 1987 Load: 34.9 t ADT: 525

Crystal River Rd.

Fair

Over: Crystal River

30 FT E OF SH133, Pitkin, CO

Built 1996 Load: 35.6 t ADT: 100

CR 19/SMITH HILL

Fair

Over: ROARING FORK RIVER

0.3 MI E OF STATE HWY 82, Pitkin, CO

Built 1986 Load: 36.3 t ADT: 5,075

SLOPESIDE LN

Fair

Over: OWL CREEK

JUST W OF PINE CREST DR, Pitkin, CO

Built 1998 Load: 36.5 t ADT: 48

SH 82 ML

Fair

Over: SNOWMASS CREEK

N edge of Snowmass, Pitkin, CO

Built 2000 Load: 36.7 t ADT: 19,000

COUNTY ROAD 4/105

Fair

Over: FRYING PAN RIVER

3 MI E OF RUEDI RESERVOIR, Pitkin, CO

Built 1988 Load: 36.7 t ADT: 197

CASTLE CK RD/CR 15

Fair

Over: CASTLE CREEK

3.5 MI SOUTH OF CO 82, Pitkin, CO

Built 1989 Load: 37.1 t ADT: 750

SH 133 ML

Fair

Over: THOMPSON CREEK

4 MI. S. OF CARBONDALE, Pitkin, CO

Built 1961 Load: 37.8 t ADT: 3,300

COUNTY ROAD 11

Fair

Over: SNOWMASS DIVIDE CREEK

1.5 MI S OF HWY 82, Pitkin, CO

Built 1985 Load: 38.5 t ADT: 1,675

COUNTY ROAD 4/105

Fair

Over: N. FORK-FRYING PAN RIVER

5 MI E OF REUDI RESERVOIR, Pitkin, CO

Built 1996 Load: 42.0 t ADT: 121

SH 82 ML

Fair

Over: MAROON CREEK

NE edge of ASPEN, Pitkin, CO

Built 2005 Load: 42.1 t ADT: 22,000

SH 133 ML

Fair

Over: COAL CREEK

AT REDSTONE, Pitkin, CO

Built 1961 Load: 43.3 t ADT: 1,800

CR17/ GERBAZ WAY

Fair

Over: ROARING FORK RIVER

JUST EAST OF HWY 82, Pitkin, CO

Built 1989 Load: 45.4 t ADT: 1,158

SH 133 ML

Fair

Over: CRYSTAL RIVER

1 MI S OF REDSTONE, Pitkin, CO

Built 1966 Load: 84.2 t ADT: 1,600

FDR 105-4B

Good

Over: FRYING PAN RV

CHAPMAN C.G., Pitkin, CO

Built 1964 Load: 17.3 t ADT: 50

SH 82 EBND ML

Good

Over: DRAW

NEAR ASPEN, Pitkin, CO

Built 2003 Load: 20.1 t ADT: 11,000

SH 82 ML-S/E Bound

Good

Over: DRAW

4.5 mi SE of Basalt, Pitkin, CO

Built 2004 Load: 20.3 t ADT: 22,000

SH 82 WBND ML

Good

Over: DRAW

NEAR ASPEN, Pitkin, CO

Built 2003 Load: 22.9 t ADT: 21,000

PINE CREST DR

Good

Over: SKI RUN

JUST W OF PINE CREST LN, Pitkin, CO

Built 1998 Load: 25.7 t ADT: 30

SH 82 ML

Good

Over: ROARING FORK RIVER

Near Basalt, Pitkin, CO

Built 1996 Load: 26.4 t ADT: 19,000

SH 82 ML

Good

Over: COUNTY ROAD

NEAR ASPEN, Pitkin, CO

Built 1994 Load: 26.6 t ADT: 22,000

SH 82 ML

Good

Over: ROARING FK RIVER

AT EASTERN EDGE OF ASPEN, Pitkin, CO

Built 1968 Load: 31.8 t ADT: 5,600

COUNTY ROAD 4

Good

Over: FRYING PAN RIVER

AT INLET TO REUDI RESERVO, Pitkin, CO

Built 1970 Load: 32.7 t ADT: 241

WOOD RD

Good

Over: TRAUMA LANE

.08 MI S OF BRUSH CR RD, Pitkin, CO

Built 2008 Load: 32.7 t ADT: 2,498

PINE CREST DR

Good

Over: SKI RUN

JUST E OF SLOPESIDE LN, Pitkin, CO

Built 1998 Load: 33.9 t ADT: 235

PINE CREST DR

Good

Over: SKI RUN

JUST E OF PINE CREST LN, Pitkin, CO

Built 1998 Load: 34.8 t ADT: 54

SH 82 EBND ML

Good

Over: DRAW

NEAR ASPEN, Pitkin, CO

Built 2003 Load: 35.6 t ADT: 11,000

SH 82 ML WBND

Good

Over: SHALE BLUFFS

NEAR ASPEN, Pitkin, CO

Built 2000 Load: 39.7 t ADT: 9,000

Related

Data sourced from official U.S. government datasets. See our methodology for details. Retrieved and formatted by PlainBridges Editorial